Title: Using a genetic algorithm to schedule the space-constrained AGV-based prefabricated bathroom units manufacturing system
Authors: Tiong, Lee Kong
Chen, Chen
Chen, I-Ming
Source: Chen, C., Tiong, L. K., & Chen, I.-M. (2018). Using a genetic algorithm to schedule the space-constrained AGV-based prefabricated bathroom units manufacturing system. International Journal of Production Research, 1-17. doi:10.1080/00207543.2018.1521532
Series/Report no.: International Journal of Production Research
Abstract: In this article, scheduling problem of a space-constrained AGV-based prefabricated bathroom units (PBU) manufacturing system is addressed. Space becomes a key resource to this manufacturing system because a very large space is required to accommodate the settling units as well as the queues. Although line balancing helps to reduce the queues, the system is still prone to deadlock due to limited space. Hence, in order to prevent deadlock situations, the production start times of PBUs have to be controlled. A genetic algorithm is proposed with the objective to decide operation for each workstation and to choose a start time for each PBU. The project duration is minimised while satisfying precedence relations and resource availabilities. A rule-based simulation approach is used to estimate the fitness value of every GA chromosomes. At last, the experiment based on data from an industrial project shows that the proposed algorithm has the potential to guide the real practice.
URI: https://hdl.handle.net/10356/106499
http://hdl.handle.net/10220/48188
ISSN: 0020-7543
DOI: 10.1080/00207543.2018.1521532
Fulltext Permission: none
Fulltext Availability: No Fulltext
Appears in Collections:CEE Journal Articles

Google ScholarTM

Check

Altmetric


Plumx

Items in DR-NTU are protected by copyright, with all rights reserved, unless otherwise indicated.